Those studies suggest that design-build, in order to yield good results on big projects, must be carried out in a collaborative spirit, with a shared interpretation of the contract terms and an experienced team leader in charge of work. Work was completed in 2018, and Kiewit has made an estimated $100-million claim tied to its costs on that project that the agency refuses to pay.Ī full copy of Travelers' research methods for its infrastructure study and results has not yet been made public, but the summary released this month echoes prior studies of design-build. There is a recent possible example, not mentioned in the study summary.Ī Kiewit-led team is in federal court with the Port Authority of New York & New Jersey over disputed costs on the $1.5-billion replacement Goethals Bridge between New Jersey and Staten Island, N.Y.